1,650m³ concrete pour at Project Fitzwilliam

1,650m³ concrete pour at Project Fitzwilliam

1,650m³ concrete pour at Project Fitzwilliam

4 Jun 2019

1,650m³ concrete pour at Project Fitzwilliam

Blog article: Successful nights work at the ESB Project Fitzwilliam last month. A 1,650m³ concrete pour, from 10pm Friday night to completion on Saturday morning. Great team effort!

Please follow the link below-

https://www.linkedin.com/feed/update/urn:li:activity:6539788159469801472

Share on:

Related posts

View more posts
Barry Casey Appointed Construction Director
14 Jul 2026

We are pleased to  announce the appointment of Barry Casey to its Main Board as Construction Director for the Southern Region (Ireland). Barry joined PJ Hegarty in 1993 and has played a key role in...

Continued Progress at Cork Airport
2 Apr 2026

On April 1st, we reached a milestone moment at Cork Airport with the official opening of Gate Post 19. The project included installing a new C3 scanner, a body scanner, and associated security equipment at...

Milestone at Railyard Apartments, Cork
30 Mar 2026

A key milestone was reached on Saturday morning at the Railyard Apartments scheme for JCD Group & Clúid in Cork city centre when we completed the slipform to the main tower core. Specialist contractor Slipform...